.png)

GKOH15-02
GKOH15-02 is a NYCDEP Green Infrastructure (GI) project to collect and manage stormwater runoff and reduce combined sewer overflows (CSO). NYCDEP’s GI Program has implemented over 13,000 right-of-way green infrastructure assets citywide, preventing millions of gallons of stormwater from entering the sewer system and reducing CSO.
GKOH15-02 is the first of multiple areawide PPCP construction contracts planned under this CSO-reduction program. Construction began in 2023 and is scheduled to be completed in 2026.
NYCDEP is constructing over 7 miles of Precast Porous Concrete Panels (PPCP) within the parking lane of roadways in the Gravesend Bay neighborhood of Brooklyn, across Community Boards 7, 12, and 14, including installation of nearly 116,370 square feet of porous pavement.
Planning and design took three years and included feasibility studies, siting locations, geotechnical investigations, topographic survey, and development of detailed design drawings and specifications; the project also addresses conflict resolution during construction and includes periodic cleaning requirements during the contractor guarantee period to maintain PPCP functionality.
![]() | ![]() |
|---|---|
![]() | ![]() |
project overview
project higlights
-
Client/Owner: NYC Department of Environmental Protection (NYCDEP) Green Infrastructure (GI) Program
-
Limits/Extent: Gravesend Bay neighborhood (Brooklyn); Community Boards 7, 12, and 14; over 7 miles within parking lanes
-
Program Context: Over 13,000 ROW GI assets implemented citywide; millions of gallons diverted from sewers; CSO reduction focus
-
Project Type: Areawide installation of Precast Porous Concrete Panels (PPCP); first of multiple areawide PPCP contracts under the program
-
Quantities/Scale: Nearly 116,370 SF of porous pavement
-
Delivery/Operations: Three-year planning/design (feasibility, siting, geotech, topo, design documents); conflict resolution during construction; periodic PPCP cleaning during the contractor guarantee period
engineering leadership
-
MIRABAL Engineering serves as a subconsultant to the REI team
MIRABAL Role
-
Oversight of construction inspection activities for areawide installation of Precast Porous Concrete Panels (PPCP) within roadway parking lanes, including verification of placement, installation sequencing, and conformance with contract requirements
-
Coordination support with NYCDEP, community stakeholders, and affected parties across Community Boards 7, 12, and 14 to maintain alignment on staging, access, and implementation across a multi-corridor, neighborhood-wide work area
-
Documentation and compliance support consistent with NYCDDC construction administration and closeout practices, including maintenance of inspection records and support for guarantee-period requirements associated with PPCP performance and periodic cleaning



